South Australia variation · ABCB Housing Provisions 2022

SA 4.2.10 Concrete

Part 4.2 Footings, slabs and associated elements · varies 4.2.10 Concrete

Open on NCC Online ↗

Delete clause 4.2.10 and insert SA 4.2.10 as follows:

Concrete must comply with the following:

Concrete must be manufactured to comply with AS 3600; and—

have a strength at 28 days of not less than 20 MPa (denoted as N20 grade); and

have a 20 mm maximum nominal aggregate size; and

have a nominal 100 mm slump.

Water must not be added to the mix to increase the slump to a value in excess of that specified.

Concrete must be placed, compacted and cured in accordance with good building practice.

Concrete in slabs must be adequately compacted, and slab surfaces, including edges, moist cured for 7 days.

After vertical surfaces are stripped of formwork, slab edges must be finished prior to curing.

Loading of concrete slabs with stacked materials or building plant must not occur for a minimum of 7 days after pouring although construction of wall frames and setting out brickwork may be undertaken during this period.

Concrete must not be poured if the air temperature on site exceeds 32ºC unless written instructions from a Professional Engineer are followed.

Same wording in ABCB Housing Provisions 2025. See ABCB Housing Provisions 2025 SA 4.2.10.

The national clause