Every Class 2, 3 or 9 building must display a notice clearly marked “FIRE ORDERS” in suitable locations near the main entrance and on each storey, explaining—

the method of operation of the fire alarm system and the location of all call-points; and

the location and methods of operation of all fire-fighting equipment; and

the location of all exits; and

the procedure for evacuation of the building.

Same wording in NCC 2025 Volume One. See NCC 2025 Volume One G4D8.
Can't meet G4D8? A Performance Solution must meet the Performance Requirements it satisfies: G4P1, G4P2, G4P3, G4P4. Start a Performance Solution →