- S30C1 ScopeThis Specification sets out the requirements for the installation of boilers and pressure vessels in buildings.
- Table S30C2 Minimum clearances for explosion reliefClearance from | Minimum clearance (metres) Adjacent wall or ceiling/roof | or 0.4 m, whichever is the greater Two walls at right angles; or one…
- S30C2 Explosion reliefThe distance between the vent of any explosion relief device for a boiler or pressure vessel and any adjacent wall, roof, ceiling or other solid…
- S30C3 Floors and drainageFloor surfaces beneath boilers and pressure vessels shall be water resistant and formed to drain away from supports and structural building…