SA H9D3 Rainwater tank capacity
SA Part H9 Water efficiency
(1) Where the roof catchment area of the building is not less than 50 m2, the building must be designed to ensure that surface water run-off from not less than 50 m2 of the roof catchment area is—
collected by a drainage system complying with H1D7; and
stored in a rainwater tank, the storage capacity of which is not less than 1 kilolitre (1000 litres); and
plumbed to at least a water closet or a water heater or all laundry cold water outlets.
(2) Where the roof catchment area of the building is less than 50 m2, all the surface water run-off from the roof catchment area must be collected, stored and plumbed in accordance with (1)(a), (b) and (c).
Not in NCC 2025. No SA H9D3 in NCC 2025 Volume Two.