New South Wales variation · ABCB Housing Provisions 2025

NSW 3.1.2 Application

NSW Part 3.1 Scope and application of Section 3 · varies 3.1.2 Application

Open on NCC Online ↗

Delete clause 3.1.2 and insert NSW 3.1.2 as follows:

(1) The application of this Section is subject to the following:

The Governing Requirements of NCC 2022 Volume Two.

Any conditions set out within the following Deemed-to-Satisfy Provisions of NCC Volume Two:

H1D3(1), for earthworks.

H2D2, for drainage.

The State and Territory variations, additions and deletions contained in the Schedules to the ABCB Housing Provisions and NCC Volume Two.

(2) Except for Table 3.2.1 as referenced by Figure 3.3.2 and except for H1D3(1) for determination of a normal site as referenced by H1D4, Part 3.2 does not apply in New South Wales.

Notes

In New South Wales requirements for shoring and adequacy of excavation works are a prescribed condition of development consent. In addition, consent authorities can place specific controls on siteworks associated with the construction of a building, by imposing further conditions on the development consent.

Changed since NCC 2022 (minor wording). See ABCB Housing Provisions 2022 NSW 3.1.2, or show what changed.

Delete clause 3.1.2 and insert NSW 3.1.2 as follows: (1) … following Deemed-to-Satisfy Provisions of NCC Volume Two: H1D3(1), for earthworks. H2D4(1)(b), H2D2, for drainage. The State and Territory variations, additions and deletions … a building, by imposing further conditions on the development consent.

Removed words are struck through; added words are highlighted. Comparison of the text only.

The national clause