NSW 4.2.3 Excavation for footings
NSW Part 4.2 Footings, slabs and associated elements · varies 4.2.3 Excavation for footings
Delete clause 4.2.3 and insert NSW 4.2.3 as follows:
(1) Excavation for footings, including thickenings for slabs and pads must be clean cut with vertical sides, wherever possible.
(2) The base of the excavation must be—
for flat sites, generally level but may slope not more than 1:40 to allow excavations to drain; and
for sloping sites at an angle of not more than 1:10; and
for stepped footings in accordance with 4.2.7.
(3) Footing excavations must be free of loose earth, tree roots, mud or debris.
(4) Topsoil containing grass roots must be removed from the site of the foundation.
(5) On loose sand sites or sites subject to wind or water erosion, the depth below finished ground level to the bottom of footings must be not less than 300 mm.
(6) The height of a finished slab-on-ground must be in accordance with 3.3.3(b).
Notes
In New South Wales requirements for shoring and adequacy of excavation works are a prescribed condition of development consent. In addition consent authorities can place specific controls on siteworks associated with the construction of a building, by imposing further conditions of development consent.