TAS E4P3 Design, construction and installation
TAS Part E4 Stormwater surface and sub-surface drainage systems
Delete clause E4P3 and insert TAS E4P3 as follows:
(1) A surface drainage installation must avoid the following:
Blockage and uncontrolled discharge.
Damage from root penetration, superimposed loads or ground movement.
Entry of sewage and/or liquid trade waste.
Entry of stormwater into a sanitary drainage.
Damage to the Network Utility Operator's drainage system
Foul air and gases accumulating in the stormwater system.
Loss to buildings or property.
(2) A surface drainage installation must ensure the following:
Access for maintenance and clearing blockages.
Stormwater is transferred to a Network Utility Operator's stormwater system or an approved disposal system.
Changed since NCC 2022. See NCC 2022 Volume Three TAS E4P3, or show what changed.
Delete clause E4P3 and insert TAS E4P3 as follows: (1) A surface drainage installation must avoid the following: Blockage … Network Utility Operator's stormwater system or an approved disposal system.
Removed words are struck through; added words are highlighted. Comparison of the text only.