F8D6 Ventilation of a roof space with the primary insulation layer parallel to the roof plane
Part F8 Condensation management
(1) In climate zones 6, 7 and 8, a roof system with the primary insulation layer installed parallel to the roof plane must have a roof space that—
is located immediately above—
the primary insulation layer; or
any control layer installed immediately above the primary insulation layer; and
is not obstructed by insulation; and
has a height not less than 18 mm, as measured perpendicular to the plane of the roof; and
for roofs less than 10 m2, is ventilated to outdoor air through openings not less than—
7,000 mm2/m provided at eaves or low level; and
5,000 mm2/m at the high level or ridge; and
for all other roofs, is ventilated to outdoor air through openings not less than—
20,000 mm2/m provided at the eaves or low level; and
5,000 mm2/m provided at the high level or ridge.
(2) Where a control layer is installed immediately above the primary insulation layer in climate zone s 6, 7 and 8, it must have a vapour permeance of not less than 1.14 μg/N.s.
(3) The requirements of (1) do not apply to a—
concrete roof; or
roof that is made of insulated sandwich panels with or without an additional ceiling linings; or
roof that is subject to Bushfire Attack Level FZ requirement in accordance with AS 3959; or
tiled roof without a control layer located above the primary insulation layer.
Figure F8D6c (explanatory) Example of a roof space in accordance with F8D6(1)(a)(ii)
Figure Notes
Roof space above the control layer, water barrier or sheathing.
Control layers immediately above primary insulation layer must have a vapour permeance of 1.14μg/N.s.