Housing Provisions clause · ABCB Housing Provisions 2022

3.3.4 Subsoil drainage

Part 3.3 Drainage · NCC 2019: 3.1.3.4

Open 3.3.4 on NCC Online ↗

Where a subsoil drainage system is installed to divert subsurface water away from the area beneath a building, the subsoil drain must—

be graded with a uniform fall of not less than 1:300; and

discharge into an external silt pit or sump with—

the level of discharge from the silt pit or sump into an impervious drainage line not less than 50 mm below the invert level of the inlet (see Figure 3.3.4); and

provision for cleaning and maintenance.

Figure 3.3.4 Construction of silt pits

Same wording in ABCB Housing Provisions 2025. See ABCB Housing Provisions 2025 3.3.4.