Deemed-to-Satisfy Provision · NCC 2022 Volume One

C4D10 Service penetrations in fire-isolated exits

Part C4 Protection of openings · NCC 2019: C3.9

Open C4D10 on NCC Online ↗

Fire-isolated exits must not be penetrated by any services other than—

electrical wiring permitted by D3D8(6) to be installed within the exit; or

ducting associated with a pressurisation system if it—

is constructed of material having an FRL of not less than –/120/60 where it passes through any other part of the building; and

does not open into any other part of the building; or

for fire services, water supply and test drain pipes.

Changed in NCC 2025. See NCC 2025 Volume One C4D10, or show what changed.

Fire-isolated exits must not be penetrated by any services other … building; or for fire services, water supply and test drain pipes. pipes; or wiring, sensors and the like required for the function and performance of a pressurisation system serving the exit.

Removed words are struck through; added words are highlighted. Comparison of the text only.

Can't meet C4D10? A Performance Solution must meet the Performance Requirements it satisfies: C1P1, C1P2, C1P3, C1P4, C1P5, C1P6, C1P7, C1P8, C1P9. Start a Performance Solution →