Verification Method · NCC 2022 Volume One

D1V2 Access to and within a building

Part D1 Access and egress · NCC 2019: DV2

Open D1V2 on NCC Online ↗

Compliance with D1P1, D1P2, D1P6, E3P4 and/or F4P1, for access, is verified when it is determined that the proposed building provides an equivalent level of access as a reference building when using the following process:

A performance-based design brief is completed to define the following:

The occupant profile and characteristics based on the type and use of the building.

The appropriate method for determining the level of access.

The appropriate modelling method and tool.

The measurable acceptance criteria.

Using the appropriate method, the level of access required is determined by first modelling a reference building using the relevant Deemed-to-Satisfy Provisions of Sections D, E and F and the occupant profile and characteristics to determine the—

needs of the occupants that the reference building addresses; and

facilities required to be accessed by each occupant profile; and

baseline measurable acceptance criteria.

The proposed building and access solution must be modelled using a modelling method and approach consistent with that used for the reference building, and the same critical features including the following:

Occupant profile and characteristics.

Building location and orientation.

Locations of all entrances and exits.

Locations of facilities important to the solution, including sanitary facilities, lifts, stairwells, etc.

The number and range of facilities.

The proposed solution’s level of access is assessed by modelling occupant performance using characteristics, whereby the proposed building provides for equivalent access appropriate to the needs of each occupant profile.

Same wording in NCC 2025 Volume One. See NCC 2025 Volume One D1V2.

Clauses referred to

Defined terms used