Deemed-to-Satisfy Provision · NCC 2022 Volume One

G5D1 Deemed-to-Satisfy Provisions

Part G5 Construction in bushfire prone areas · NCC 2019: G5.0

Open G5D1 on NCC Online ↗
Varied in SA. Check the variation for your state.

(1) Where a Deemed-to-Satisfy Solution is proposed, Performance Requirements G5P1 and subject to G5D2, G5P2, are satisfied by complying with G5D3 and G5D4.

(2) Where a Performance Solution is proposed, the relevant Performance Requirements must be determined in accordance with A2G2(3) and A2G4(3) as applicable.

Same wording in NCC 2025 Volume One. See NCC 2025 Volume One G5D1.

State and territory variations all clauses side by side →

Clauses referred to

Defined terms used