J1V4 Verification of building envelope sealing
Part J1 Energy efficiency performance requirements · NCC 2019: JV4
(1) Compliance with J1P1(e) and J1P2 is verified for building envelope sealing when the envelope is sealed at an air permeability rate, tested in accordance with Method 1 of AS/NZS ISO 9972, of not more than—
for a Class 2 building or a Class 4 part of a building, 10 m³/hr.m² at 50 Pa reference pressure; or
for a Class 5, 6, 8 or 9a or 9b building, other than a ward area, in climate zones 1, 7 and 8, 5 m³/hr.m² at 50 Pa reference pressure; or
for a Class 3 or 9c building, or a Class 9a ward area in climate zones 1, 3, 4, 6, 7 and 8, 5 m³/hr.m² at 50 Pa reference pressure.
(2) In a sole-occupancy unit of a Class 2 building or a Class 4 part of a building, where an air permeability rate of not more than 5 m3/hr.m2 at 50 Pa reference pressure is achieved—
a mechanical ventilation system must be provided that—
can be manually overridden; and
provides outdoor air, either—
continuously; or
intermittently, where the system has controls that enable operation for not less than 25 per cent of each 4 hour segment; and
provides a flow rate not less than that achieved with the following formula: [formula] , where—
[formula] = the required air flow rate (L/s); and
[formula] = the total area of the sole-occupancy unit of a Class 2 or Class 4 part of a building (m2); and
[formula] = the number of bedrooms in the sole-occupancy unit of a Class 2 or Class 4 part of a building; and
[formula] = the fraction of time within each 4 hour segment that the system is operational; and
any space with a solid-fuel burning combustion appliance must be ventilated with permanent openings directly to outside with a free area of not less than half of the cross-sectional area of the appliance’s flue; and
any space with a gas-fueled combustion appliance must be ventilated in accordance with—
clause 6.4 of AS/NZS 5601.1; and
clause 6.4.5 of AS/NZS 5601.1.
(3) For the purposes of (2)(c), the volume of the space is considered to be 1 m3 for determining ventilation requirements.
Changed in NCC 2025. See NCC 2025 Volume One J1V4, or show what changed.
(1) Compliance with J1P1(e) J1P1(a) and J1P2 is verified for building envelope sealing when the … ISO 9972, of not more than — for a Class 2 building or a Class 4 part of a building, 10 m³/hr.m² at 50 Pa reference pressure; or for a Class 5, 6, 8 or 8, 9a or 9b building, other than a ward area, in … 8, 5 m³/hr.m² at 50 Pa reference pressure. (2) In a sole-occupancy unit of a Class 2 building or a Class 4 part of a building, where an air … system has controls that enable operation for not less than 25 per cent 25% of each 4 hour segment; and provides a flow rate … rate (L/s); and [formula] = the total area of the sole-occupancy unit of a Class 2 or Class 4 part of a building (m2); and [formula] = the number of bedrooms in the sole-occupancy unit of a Class 2 or Class 4 part of a building; and [formula] = the … is considered to be 1 m3 for determining ventilation requirements.
Removed words are struck through; added words are highlighted. Comparison of the text only.