J4D3 Thermal construction — general
Part J4 Building fabric · NCC 2019: J1.2, NSW J(A)1.2
(1) Where required, insulation must comply with AS/NZS 4859.1 and be installed so that it—
abuts or overlaps adjoining insulation other than at supporting members such as studs, noggings, joists, furring channels and the like where the insulation must be against the member; and
forms a continuous barrier with ceilings, walls, bulkheads, floors or the like that inherently contribute to the thermal barrier; and
does not affect the safe or effective operation of a service or fitting.
(2) Where required, reflective insulation must be installed with—
the necessary airspace to achieve the required R-Value between a reflective side of the reflective insulation and a building lining or cladding; and
the reflective insulation closely fitted against any penetration, door or window opening; and
the reflective insulation adequately supported by framing members; and
each adjoining sheet of roll membrane being—
overlapped not less than 50 mm; or
taped together.
(3) Where required, bulk insulation must be installed so that—
it maintains its position and thickness, other than where it is compressed between cladding and supporting members, water pipes, electrical cabling or the like; and
in a ceiling, where there is no bulk insulation or reflective insulation in the wall beneath, it overlaps the wall by not less than 50 mm.
(4) Roof, ceiling, wall and floor materials, and associated surfaces are deemed to have the thermal properties listed in Specification 36.
(5) The required Total R-Value and Total System U-Value, including allowance for thermal bridging, must be—
calculated in accordance with AS/NZS 4859.2 for a roof or floor; or
determined in accordance with Specification 37 for wall-glazing construction; or
determined in accordance with Specification 39 or Section 3.5 of CIBSE Guide A for soil or sub-floor spaces.
Changed in NCC 2025. See NCC 2025 Volume One J4D3, or show what changed.
(1) Where required, insulation must comply with AS/NZS 4859.1 and be installed so that it — forms a continuous barrier with ceilings, walls, bulkheads, floors, slab-edges or the like that inherently contribute to the thermal barrier; and is continuous below and around box gutters, parapets and the like; and abuts or overlaps adjoining insulation other than at supporting members such as posts, beams, truss chords, rafters, studs, noggings, joists, furring channels channels, slab edges and the like where the insulation must be against the member; and forms a continuous barrier with ceilings, walls, bulkheads, floors or the like that inherently contribute to the thermal barrier; and does not affect the safe or effective operation of … 3.5 of CIBSE Guide A for soil or sub-floor spaces.
Removed words are struck through; added words are highlighted. Comparison of the text only.