Deemed-to-Satisfy Provision · NCC 2022 Volume One

J4D7 Floors

Part J4 Building fabric · NCC 2019: J1.6

Open J4D7 on NCC Online ↗

(1) A floor must achieve the Total R-Value specified in Table J4D7.

(2) For the purposes of (1), a slab-on-ground that does not have an in-slab heating or cooling system is considered to achieve a Total R-Value of R2.0, except—

in climate zone 8; or

a Class 3, Class 9a ward area or Class 9b building in climate zone 7 that has a floor area to floor perimeter ratio of less than or equal to 2.

(3) A floor must be insulated around the vertical edge of its perimeter with insulation having an R-Value greater than or equal to 1.0 when the floor—

is a concrete slab-on-ground in climate zone 8; or

has an in-slab or in-screed heating or cooling system, except where used solely in a bathroom, amenity area or the like.

(4) Insulation required by (3) for a concrete slab-on-ground must—

be water resistant; and

be continuous from the adjacent finished ground level—

to a depth not less than 300 mm; or

for the full depth of the vertical edge of the concrete slab-on-ground.

Table J4D7 Floors – Minimum Total R-Value

Location

Climate zone 1— upwards heat flow

Climate zones 2 and 3 — upwards and downwards heat flow

Climate zones 4, 5, 6 and 7 — downwards heat flow

Climate zone 8 — downwards heat flow

A floor without an in-slab heating or cooling system

2.0

2.0

2.0

3.5

A floor with an in-slab heating or cooling system

3.25

3.25

3.25

4.75

Table Notes

For the purpose of calculating the Total R-Value of a floor, the sub-floor and soil R-Value must be calculated in accordance with Specification 39 or Section 3.5 of CIBSE Guide A.

Tables

Changed in NCC 2025 (minor wording). See NCC 2025 Volume One J4D7, or show what changed.

(1) A floor must achieve the Total R-Value specified in … or a Class 3, Class 9a ward area or Class 9b 9c building in climate zone 7 that has a floor area … with Specification 39 or Section 3.5 of CIBSE Guide A.

Removed words are struck through; added words are highlighted. Comparison of the text only.

Can't meet J4D7? A Performance Solution must meet the Performance Requirements it satisfies: J1P1, J1P2, J1P3, J1P4. Start a Performance Solution →

Defined terms used