Northern Territory variation · NCC 2022 Volume One
NT F7D1 Deemed-to-Satisfy Provisions
NT Part F7 Sound transmission and insulation · varies F7D1 Deemed-to-Satisfy Provisions
(1) Where a Deemed-to-Satisfy Solution is proposed, Performance Requirements F7P1 to F7P4 are satisfied by complying with NT F7D2 to NT F7D9.
(2) Where a Performance Solution is proposed, the relevant Performance Requirements must be determined in accordance with A2G2(3) and A2G4(3) as applicable.
Changed in NCC 2025. See NCC 2025 Volume One NT F7D1, or show what changed.
Insert NT clause F7D1 in clause F7D1 as follows: (1) Where a Deemed-to-Satisfy Solution is proposed, Performance Requirements F7P1 … be determined in accordance with A2G2(3) and A2G4(3) as applicable.
Removed words are struck through; added words are highlighted. Comparison of the text only.