Delete clause B2D9 and insert SA B2D9 as follows:

A heated water service must be in accordance with AS/NZS 3500.4 with the following variations—

substitute AS/NZS 3500.4 clause 5.8(c) with: 5.8(c) All new or replacement unvented storage water heaters shall be fitted with new temperature/pressure relief and expansion control valves.

substitute AS/NZS 3500.4 clause 5.11.2.1 with: 5.11.2.1 The drain lines from the outlet of the temperature/pressure-relief valve and the expansion control valve on an individual water heater shall not be interconnected.

substitute AS/NZS 3500.4 clause 5.11.3(e) with: 5.11.3(e) All drain lines shall discharge separately over a gully, tundish or other visible approved outlet.

Same wording in NCC 2025 Volume Three. See NCC 2025 Volume Three SA B2D9.