TAS E4P1 Surface drainage systems

TAS Part E4 Stormwater surface and sub-surface drainage systems

Open on NCC Online ↗

(1) A surface drainage system must have capacity to transfer the volume of water anticipated in an annual exceedance probability rainfall event.

(2) The annual exceedance probability must be appropriate to the—

importance of the building; and

severity of potential damage to property, loss of amenity, illness or injury that would result from the failure of the system.

Changed in NCC 2025. See NCC 2025 Volume Three TAS E4P1, or show what changed.

Delete clause E4P1 and insert TAS E4P1 as follows: (1) A surface drainage system must have capacity to transfer … injury that would result from the failure of the system.