Baths and spas, except freestanding baths and spas, must—

have an upturn lip; and

be recessed into the wall (see Figure 10.2.20); and

have the water resistant substrate materials of the wall pass down inside the upturn lip (see Figure 10.2.20).

Figure 10.2.20 Typical bath junctions

Figure Notes

Rebating of timber and steel framed walls must be in accordance with AS 1684 or NASH Standard Part 2 as appropriate.

Where rebating of masonry walls is required, it must be accommodated for in the design in accordance with AS 3700.

For diagram (c), where a waterstop cannot be provided, a Type 1 or Type 2 junction can be used with AS 3740.