Table 10.8.1 Vapour permeance requirements
Part 10.8 Condensation management
| Climate zone | Wall construction | Vapour permeance (µg/N.s) |
|---|---|---|
| 1 | No cavity | ≥ 0.0022 to < 1.1403 |
| Drained and ventilated cavity | ≥ 0 to < 1.1403 | |
| 3 | No cavity | ≥ 0.1429 |
| Drained and ventilated cavity | ≥ 0.0022 | |
| 4, 5 | No cavity | ≥ 1.1403 |
| Drained and ventilated cavity | ≥ 0.1429 | |
| 6, 7, 8 | No cavity | X |
| Drained and ventilated cavity | ≥ 1.1403 |
Table Notes
X = A cavity must be provided in climate zones 6, 7 and 8.
Table for 10.8.1 External wall construction
New in NCC 2025. No Table 10.8.1 in ABCB Housing Provisions 2022; it may have moved or been renumbered.