ABCB Housing Provisions 2025
Part 10.8 Condensation management
6 clauses · Open on NCC Online ↗
- Table 10.8.1 Vapour permeance requirementsClimate zone | Wall construction | Vapour permeance (µg/N.s) 1 | No cavity | ≥ 0.0022 to < 1.1403 Drained and ventilated cavity | ≥ 0 to < 1.1403 3…
- 10.8.1 External wall constructionWhere a pliable building membrane or a sarking-type material is installed as a control layer in an external wall, it must— comply with AS 4200.1;…
- 10.8.2 Exhaust systemsAn exhaust system installed in a kitchen, bathroom, sanitary compartment or laundry must have a minimum flow rate of— 25 L/s for a bathroom or…
- Table 10.8.3 Roof space ventilation requirementsRoof pitch | Ventilation openings < 10° | 20,000 mm2/m provided at eaves or low level, or at each of two opposing ends for gable roofs For roofs…
- 10.8.3 Ventilation of a roof space with the primary insulation layer not parallel to the roof planeIn climate zones 6, 7 and 8, a roof with the primary insulation layer not parallel to the roof plane must have a roof space that— has a height of…
- 10.8.4 Ventilation of a roof space with the primary insulation layer parallel to the roof planeIn climate zones 6, 7 and 8, a roof system with the primary insulation layer installed parallel to the roof plane must have a roof space that— is…