Table · ABCB Housing Provisions 2025

Table 13.2.3t Metal-framed flat, skillion or cathedral roof – minimum Total R-Value to account for thermal bridging

Part 13.2 Building fabric

Open Table 13.2.3t on NCC Online ↗
Minimum ceiling insulation R-Value from Tables 13.2.3j to 13.2.3rMinimum Total R-Value to account for thermal bridging – heat flow downMinimum Total R-Value to account for thermal bridging – heat flow up
1.01.401.32
1.51.861.78
2.02.292.21
2.52.712.63
3.03.113.02
3.53.313.22
4.03.663.57
4.53.983.90
5.04.324.22
5.54.634.53
6.04.934.82

Table Notes

Minimum Total R-Values are in-situ values. They account for compression of insulation.

Direction of heat flow must be determined in accordance with Table 13.2.3v.

Table for 13.2.3 Roofs and ceilings

Same wording in ABCB Housing Provisions 2022. See ABCB Housing Provisions 2022 Table 13.2.3t.

Defined terms used