NSW C2P7 Damage
NSW Part C2 Sanitary drainage systems · varies C2P7 Damage
Delete clause C2P7 and insert NSW C2P7 as follows:
(1) Damage to sanitary drainage systems from superimposed loads must be avoided.
(2) Damage to sanitary drainage systems from ground movement must be avoided.
(3) Damage to sanitary drainage systems from root penetration must be avoided.
(4) Damage to the Network Utility Operator's sewerage system or any approved disposal system must be avoided.
(5) Damage to siteworks or existing buildings from a sanitary drainage system must be avoided.
Notes
Deemed-to-Satisfy Provisions for the use of flexible joints in sanitary drainage systems to address ground movement can be found in the NSW C2D4. Other installation methods to avoid damage from superimposed loads, or ground movement to a sanitary drainage system require the submission of a Performance Solution to the Plumbing Regulator.