Victoria variation · NCC 2025 Volume Three

VIC E3D2 General requirements

VIC Part E3 Stormwater - Roof drainage systems

Open on NCC Online ↗

Delete clause E3D2 and insert VIC E3D2 as follows:

(1) The design, construction, installation, replacement, repair, alteration and maintenance of a roof drainage system must be in accordance with AS/NZS 3500.3 and SA HB 39.

(2) Where there are any conflicts between AS/NZS 3500.3 and SA HB 39, AS/NZS 3500.3 prevails.

Changed since NCC 2022. See NCC 2022 Volume Three VIC E3D2, or show what changed.

Delete clause E3D2 and insert VIC E3D2 as follows: (1) The design, construction, installation, replacement, repair, alteration and maintenance of a roof drainage system must be in accordance with AS/NZS 3500.3 and SA HB 39, subject to following: Insert Clause 4.9.6.3 Fastening in AS/NZS 3500.3 as follows: Dowpipes to be securely fastened to walls and structures so as to withstand movement due to thermal expansion or weight due to a partial or total blockage, and 39. (2) Where there are any conflicts between AS/NZS 3500.3 and SA HB 39, AS/NZS 3500.3 prevails.

Removed words are struck through; added words are highlighted. Comparison of the text only.

Other states and territories