VIC E3P4 Design, construction and installation
VIC Part E3 Stormwater - Roof drainage systems
Delete clause E3P4 and insert VIC E3P4 as follows:
(1) A roof drainage system must ensure the following—
Stormwater is transferred to a point of connection.
Access for maintenance and clearing blockages.
(2) A roof drainage installation must avoid the following—
Loss of amenity due to blockages and uncontrolled discharge.
Foul air and gases accumulating in the roof drainage system.
Loss to buildings and property amenity due to blockages and uncontrolled discharge.
Changed since NCC 2022. See NCC 2022 Volume Three VIC E3P4, or show what changed.
Delete clause E3P4 and insert VIC E3P4 as follows: (1) A roof drainage system must ensure the following — … buildings and property amenity due to blockages and uncontrolled discharge.
Removed words are struck through; added words are highlighted. Comparison of the text only.