Delete clause B2D9 and insert WA B2D9 as follows:

A heated water service must be in accordance with AS/NZS 3500.4 with the following variations:

For clause 5.8 delete Note 1 and insert: Note 1 - An expansion control valve or expansion vessel must be incorporated in the installation of an unvented water heater otherwise the temperature/pressure relief valve may become blocked due to the deposition of calcium carbonate from the heated water that is relieved during thermal expansion. See Figures 5.9.4(C) and 5.9.(D)(a).

For Table 5.9.1(A), in the row relating to Expansion control valve or expansion vessel (Australia only) in the 3rd and 4th columns deleted “g” and insert: Yes.

New in NCC 2025. No WA B2D9 in NCC 2022 Volume Three; it may have moved or been renumbered.