Verification Method · NCC 2025 Volume One

C1V2 Fire spread between buildings on the same allotment

Part C1 Fire resistance · NCC 2019: CV2

Open C1V2 on NCC Online ↗

Compliance with C1P2(1)(c) to avoid the spread of fire between buildings on the same allotment is verified when, for the distances between buildings set out in Column 1 of Table C1V2, it is calculated that a building—

is capable of withstanding the heat flux set out in Column 2 of Table C1V2 without ignition; and

will not cause heat flux in excess of those set out in Column 2 of Table C1V2.

Table C1V2 Fire spread between buildings on the same allotment

Column 1 (Distance between buildings on the same allotment (m))

Column 2 (Heat flux (kW/m2))

0

80

2

40

6

20

12

10