Deemed-to-Satisfy Provision · NCC 2025 Volume One

C3D11 Separation of lift shafts

Part C3 Compartmentation and separation · NCC 2019: C2.10

Open C3D11 on NCC Online ↗

(1) Any lift connecting more than 2 storeys, or more than 3 storeys if the building is sprinklered, (other than lifts which are wholly within an atrium) must be separated from the remainder of the building by enclosure in a shaft in which—

in a building required to be of Type A construction — the walls have the relevant FRL prescribed by Specification 5; and

in a building required to be of Type B construction — the walls—

if load bearing, have the relevant FRL prescribed by Table S5C21e; or

if non-load bearing, be of non-combustible construction.

(2) Any lift in a patient care area in a Class 9a health-care building or a resident use area in Class 9c building must be separated from the remainder of the building by a shaft having an FRL of not less than—

in a building of Type A or B construction — 120/120/120; or

in a building of Type C construction — 60/60/60.

(3) An emergency lift must be contained within a fire-resisting shaft having an FRL of not less than 120/120/120.

(4) Openings for lift landing doors and services must be protected in accordance with the Deemed-to-Satisfy Provisions of Part C4.

New in NCC 2025. No C3D11 in NCC 2022 Volume One; it may have moved or been renumbered.
Can't meet C3D11? A Performance Solution must meet the Performance Requirements it satisfies: C1P1, C1P2, C1P3, C1P4, C1P5, C1P6, C1P7, C1P8, C1P9. Start a Performance Solution →