Deemed-to-Satisfy Provision · NCC 2025 Volume One

D2D11 Determination and measurement of exits and paths of travel to exits

Part D2 Provision for escape · NCC 2019: D1.6(h) and (i)

Open D2D11 on NCC Online ↗

For the purposes of D2D7 to D2D10 the following apply:

The required width of a stairway or ramp in a required exit or path of travel to an exit must—

be measured clear of all obstructions such as handrails, projecting parts of barriers and the like; and

extend without interruption, except for ceiling cornices, to a height not less than 2 m vertically above a line along the nosings of the treads or the floor surface of the ramp or landing.

To determine the aggregate unobstructed width, the number of persons accommodated must be calculated according to D2D18.

Same wording in NCC 2022 Volume One. See NCC 2022 Volume One D2D11.
Can't meet D2D11? A Performance Solution must meet the Performance Requirements it satisfies: D1P1, D1P2, D1P3, D1P4, D1P5, D1P6, D1P8, D1P10, D1P9. Start a Performance Solution →