New South Wales variation · NCC 2025 Volume One
NSW J9D2 Application of Part
NSW Part J9 Energy monitoring and on-site distributed energy resources · varies J9D2 Application of Part
Delete clause J9D2 and insert NSW J9D2 as follows:
The Deemed-to-Satisfy Provisions of this Part do not apply to a Class 8 electricity network substation.
New in NCC 2025. No NSW J9D2 in NCC 2022 Volume One; it may have moved or been renumbered.