2.2.3 Determination of individual actions
Part 2.2 Structural provisions · NCC 2019: 3.0.3
The magnitude of individual actions must be determined in accordance with the following:
Permanent actions:
the design or known dimensions of the building or structure; and
the unit weight of the construction; and
AS/NZS 1170.1.
Imposed actions:
the known loads that will be imposed during the occupation or use of the building or structure; and
construction activity actions; and
AS/NZS 1170.1.
Wind, snow and earthquake actions:
the applicable annual probability of design event for safety, determined by—
assigning the building or structure an Importance Level in accordance with Table 2.2.3a; and
determining the corresponding annual probability of exceedance for safety in accordance with Table 2.2.3b; and
for wind actions, AS/NZS 1170.2 or AS 4055; and
for snow and ice actions, AS/NZS 1170.3; and
for earthquake actions, AS 1170.4.
Actions not covered in (a), (b) and (c) above:
the nature of the action; and
the nature of the building or structure; and
the Importance Level of the building or structure determined in accordance with Table 2.2.3a; and
AS/NZS 1170.1.
For the purposes of (d) the actions include but are not limited to—
liquid pressure action; and
ground water action; and
rainwater action (including ponding action); and
earth pressure action; and
differential movement; and
time dependent effects (including creep and shrinkage); and
thermal effects; and
ground movement caused by—
swelling, shrinkage or freezing of the subsoil; and
landslip or subsidence; and
siteworks associated with the building or structure; and
construction activity actions.
Table 2.2.3a Importance Levels of buildings and structures
Importance Level
Building types
1
Buildings or structures presenting a low degree of hazard to life and other property in the case of failure.
2
Buildings or structures not included in Importance Level 1.
Table 2.2.3b Design events for safety—annual probability of exceedance
Importance Level
Non-cyclonic wind
Cyclonic wind
Snow
Earthquake
1
1:100
1:200
1:100
1:250
2
1:500
1:500
1:150
1:500
Figure 2.2.3 Wind regions
Tables
- Table 2.2.3a Importance Levels of buildings and structures
- Table 2.2.3b Design events for safety—annual probability of exceedance
Changed in NCC 2025. See ABCB Housing Provisions 2025 2.2.3, or show what changed.
The magnitude of individual actions must be determined in accordance … in Importance Level 1. Table 2.2.3b Design events for safety —annual — annual probability of exceedance Importance Level Non-cyclonic wind Cyclonic wind (wind regions B2 and C) Cyclonic wind (wind region D) Snow Earthquake 1 1:100 1:200 1:250 1:100 1:250 2 1:500 1:500 1:1000 1:150 1:500 Figure 2.2.3 Wind regions
Removed words are struck through; added words are highlighted. Comparison of the text only.