Table 13.2.5u Masonry veneer metal-framed walls – thermal bridging mitigation

Part 13.2 Building fabric

Open Table 13.2.5u on NCC Online ↗
Wall insulation R-Value from Tables 13.2.5c, 13.2.5g, 13.2.5i, 13.2.5k and 13.2.5mThermal bridging mitigation options
> 0Either install reflective insulation outside the frame to a minimum 20 mm reflective airspace between the frame and veneer, or add a layer of continuous insulation with an R-Value of at least R0.30 on the inside or the outside of the frame.

Table Notes

Minimum R-Values are in-situ values. They account for compression of insulation.

The surface emittance of a reflective surface facing an airspace must be a maximum of 0.1.

Table for 13.2.5 External walls

Same wording in ABCB Housing Provisions 2025. See ABCB Housing Provisions 2025 Table 13.2.5u.

Defined terms used