Table · ABCB Housing Provisions 2022

Table 6.2.1b Ground clearance

Part 6.2 Subfloor ventilation

Open Table 6.2.1b on NCC Online ↗
Climatic zone (see Figure 6.2.1a)Minimum ground clearance height where termite inspection or management system is not required (mm)Minimum ground clearance height where termite inspection is required (mm)
A, B and C150400

Table Notes

400 mm clearance required only where termite management systems are installed that need to be inspected (see Part 2.2.4).

On sloping sites the 400 mm clearance required by (1) may be reduced to 150 mm within 2 m of external walls in accordance with Figure 6.2.1b.

Table for 6.2.1 Subfloor ventilation

Same wording in ABCB Housing Provisions 2025. See ABCB Housing Provisions 2025 Table 6.2.1b.

Clauses referred to

Defined terms used