Performance Requirement · NCC 2022 Volume One

B1P1 Structural reliability

Part B1 Structural provisions · NCC 2019: BP1.1

Open B1P1 on NCC Online ↗

(1) By resisting the actions to which it may reasonably be expected to be subjected, a building or structure, during construction and use, with appropriate degrees of reliability, must—

perform adequately under all reasonably expected design actions; and

withstand extreme or frequently repeated design actions; and

be designed to sustain local damage, with the structural system as a whole remaining stable and not being damaged to an extent disproportionate to the original local damage; and

avoid causing damage to other properties.

(2) The actions to be considered to satisfy (1) include but are not limited to—

permanent actions (dead loads) including, for a Class 7b building, an additional notional permanent roof load of not less than 0.15 kPa to support the addition of solar photovoltaic panels; and

imposed actions (live loads arising from occupancy and use); and

wind action; and

earthquake action; and

snow action; and

liquid pressure action; and

ground water action; and

rainwater action (including ponding action); and

earth pressure action; and

differential movement; and

time dependent effects (including creep and shrinkage); and

thermal effects; and

ground movement caused by—

swelling, shrinkage or freezing of the subsoil; and

landslip or subsidence; and

siteworks associated with the building or structure; and

construction activity actions; and

termite actions.

Exemptions

The requirement for an additional notional permanent roof load to support photovoltaic panels in B1P1(2)(a) does not apply to a Class 7b building—

where 100% of the roof area is shaded for more than 70% of daylight hours; or

with a roof area of not more than 55 m2; or

where more than 50% of the roof area is used as a terrace, carpark, roof garden, roof light or the like.

Notes

The requirement in B1P1(2)(a) to consider, for a Class 7b building, an additional notional permanent roof load of not less than 0.15 kPa to support the addition of solar photovoltaic panels does not take effect until 1 October 2023.

Changed in NCC 2025. See NCC 2025 Volume One B1P1, or show what changed.

(1) By resisting the actions to which it may reasonably … a building or structure, during construction and use, with appropriate degrees levels of reliability, must — perform adequately under all reasonably expected … local damage; and avoid causing damage to other properties. (2) Each component of the building or structure must withstand all actions with the minimum levels of reliability specified in Tables B1P1a, B1P1b and B1P1c as determined in accordance with B1V1. (3) The actions to be considered to satisfy (1) and (2) include but are not limited to — permanent actions (dead … building or structure; and construction activity actions; and termite actions. (4) The structural resistance of materials and forms of construction must be determined using material properties with appropriate allowance for the type and use of the material and the degree of accuracy inherent in the methods used to assess the structural behaviour. (5) For the purposes of B1P1(2), Importance Level must be assigned in accordance with Table B1P1d. Table B1P1a Minimum annual reliability indices (β) for additive load combinations (gravity actions only) All Importance Levels β = 4.30 Table Notes The annual reliability indices in Table B1P1a must be met for all components necessary to comply with B1P1(1) at the relevant Importance Level. Ancillary components may have a reliability index appropriate to the component, but not less than that required for Importance Level 1, irrespective of the Importance Level of the whole building or structure. Table B1P1b Minimum annual reliability indices (β) for additive load combinations (combined gravity and other actions) Importance Level 1 Importance Level 2 Importance Level 3 Importance Level 4 β = 3.45 β = 3.70 β = 3.85 β = 4.00 Table Notes The annual reliability indices in Table B1P1b must be met for all components necessary to comply with B1P1(1) at the relevant Importance Level. Ancillary components may have a reliability index appropriate to the component, but not less than that required for Importance Level 1, irrespective of the Importance Level of the whole building or structure. Table B1P1c Minimum annual reliability indices (β) for action reversal and stability load combinations (combined gravity and other actions) Importance Level 1 Importance Level 2 Importance Level 3 Importance Level 4 β = 3.00 β = 3.35 β = 3.55 β = 3.65 Table Notes The annual reliability indices in Table B1P1c must be met for all components necessary to comply with B1P1(1) at the relevant Importance Level. Ancillary components may have a reliability index appropriate to the component, but not less than that required for Importance Level 1, irrespective of the Importance Level of the whole building or structure. Table B1P1d Importance Levels of buildings and structures Importance Level Building Types 1 Buildings or structures presenting a low degree of hazard to life and other property in the case of failure. 2 Buildings or structures not included in Importance Level 1, 3 and 4. 3 Buildings or structures that are designed to contain a large number of people. 4 Buildings or structures that are essential to post-disaster recovery or associated with hazardous facilities. Exemptions The requirement for an additional notional permanent roof load to support photovoltaic panels in B1P1(2)(a) B1P1(3)(a) does not apply to a Class 7b building — where … terrace, carpark, roof garden, roof light or the like. Notes The requirement in B1P1(2)(a) to consider, for a Class 7b building, an additional notional permanent roof load of not less than 0.15 kPa to support the addition of solar photovoltaic panels B1P1(2) does not take effect until 1 October 2023. year after the adoption date for NCC 2025. Notes When assessing compliance with B1P1(3)(a) to (e), the actions must include those from the relevant part of AS/NZS 1170 series of Standards.

Removed words are struck through; added words are highlighted. Comparison of the text only.

Defined terms used