Deemed-to-Satisfy Provision · NCC 2022 Volume One

C2D11 Fire hazard properties

Part C2 Fire resistance and stability · NCC 2019: C1.10 and NSW C1.10, C1.10

Open C2D11 on NCC Online ↗
Varied in NSW, VIC. Check the variation for your state.

(1) The fire hazard properties of the following internal linings, materials and assemblies within a Class 2 to 9 building must comply with Specification 7:

Floor linings and floor coverings.

Wall linings and ceiling linings.

Air-handling ductwork.

Lift cars.

In Class 9b buildings used as a theatre, public hall or the like—

fixed seating in the audience area or auditorium; and

a proscenium curtain required by Specification 32.

Escalators, moving walkways and non-required non fire-isolated stairways or pedestrian ramps subject to Specification 14.

Sarking-type materials.

Attachments to floors, ceilings, internal walls, common walls, fire walls and to internal linings of external walls.

Other materials including insulation materials other than sarking-type materials.

(2) Paint or fire-retardant coatings must not be used to achieve compliance with the required fire hazard properties.

(3) The requirements of (1) do not apply to a material or assembly if it is—

plaster, cement render, concrete, terrazzo, ceramic tile or the like; or

a fire-protective covering; or

a timber-framed window; or

a solid timber handrail or skirting; or

a timber-faced door; or

an electrical switch, socket-outlet, cover plate or the like; or

a material used for—

a roof insulating material applied in continuous contact with a substrate; or

an adhesive; or

a damp-proof course, flashing, caulking, sealing, ground moisture barrier, or the like; or

a paint, varnish, lacquer or similar finish, other than nitro-cellulose lacquer; or

a clear or translucent roof light of glass fibre-reinforced polyester if—

the roof in which it is installed forms part of a single storey building required to be Type C construction; and

the material is used as part of the roof covering; and

it is not closer than 1.5 m from another roof light of the same type; and

each roof light is not more than 14 m2 in area; and

the area of the roof lights per 70 m2 of roof surface is not more than 14 m2; or

a face plate or neck adaptor of supply and return air outlets of an air handling system; or

a face plate or diffuser plate of light fitting and emergency exit signs and associated electrical wiring and electrical components; or

a joinery unit, cupboard, shelving, or the like; or

an attached non-building fixture and fitting such as—

a curtain, blind, or similar decor, other than a proscenium curtain required by Specification 32; and

a whiteboard, window treatment or the like; or

timber treads, risers, landings and associated supporting framework installed in accordance with D3D30 where the Spread-of-Flame Index and the Smoke-Developed Index of the timber does not exceed 9 and 8 respectively; or

any other material that does not significantly increase the hazards of fire.

Same wording in NCC 2025 Volume One. See NCC 2025 Volume One C2D11.
Can't meet C2D11? A Performance Solution must meet the Performance Requirements it satisfies: C1P1, C1P2, C1P3, C1P4, C1P5, C1P6, C1P7, C1P8, C1P9. Start a Performance Solution →

State and territory variations all clauses side by side →

Clauses referred to

Defined terms used