Deemed-to-Satisfy Provision · NCC 2022 Volume One

E1D12 Where sprinklers are required: additional requirements

Part E1 Fire fighting equipment · NCC 2019: Table E1.5

Open E1D12 on NCC Online ↗

(1) For sprinkler requirements for atriums, see Part G3.

(2) For sprinkler requirements for large isolated buildings, see C3D4.

Same wording in NCC 2025 Volume One. See NCC 2025 Volume One E1D12.
Can't meet E1D12? A Performance Solution must meet the Performance Requirements it satisfies: E1P1, E1P2, E1P3, E1P4, E1P5, E1P6. Start a Performance Solution →