Deemed-to-Satisfy Provision · NCC 2022 Volume One

E1D15 Fire control centres

Part E1 Fire fighting equipment · NCC 2019: E1.8

Open E1D15 on NCC Online ↗

A fire control centre facility in accordance with Specification 19 must be provided for—

a building with an effective height of more than 25 m; and

a Class 6, 7, 8 or 9 building with a total floor area of more than 18 000 m2.

Same wording in NCC 2025 Volume One. See NCC 2025 Volume One E1D15.
Can't meet E1D15? A Performance Solution must meet the Performance Requirements it satisfies: E1P1, E1P2, E1P3, E1P4, E1P5, E1P6. Start a Performance Solution →

Defined terms used