Victoria variation · NCC 2022 Volume One

VIC A2G2 Performance Solution

Part A2 Compliance with the NCC · varies A2G2 Performance Solution

Open on NCC Online ↗

Insert VIC subclause A2G2(5) in clause A2G2 as follows:

(5) A Performance Solution cannot be used to satisfy a relevant Performance Requirement for the installation of a combustible cladding product in an external wall of a—

Class 2, 3 or 9 building with a rise in storeys of 2 that does not comply with C2D6; and

Class 2, 3, 5, 6, 7, 8 or 9 building with a rise in storeys of 3 or more.

Changed in NCC 2025. See NCC 2025 Volume One VIC A2G2, or show what changed.

Insert Delete clause A2G2 and insert VIC subclause A2G2(5) in clause A2G2 as follows: (1) A Performance Solution is achieved by demonstrating — compliance with all relevant Performance Requirements; or the solution is at least equivalent to the Deemed-to-Satisfy Provisions. (2) A Performance Solution must be shown to comply with the relevant Performance Requirements through one or a combination of the following Assessment Methods: Evidence of suitability in accordance with Part A5 that shows the use of a material, product, plumbing and drainage product, form of construction or design meets the relevant Performance Requirements. A Verification Method including the following: The Verification Methods provided in the NCC. Other Verification Methods, accepted by the appropriate authority that show compliance with the relevant Performance Requirements. Expert Judgement. Comparison with the Deemed-to-Satisfy Provisions. (3) Where a Performance Requirement is satisfied entirely by a Performance Solution, in order to comply with (1) the following method must be used to determine the Performance Requirement or Performance Requirements relevant to the Performance Solution: Identify the relevant Performance Requirements from the Section or Part to which the Performance Solution applies. Identify Performance Requirements from other Sections or Parts that are relevant to any aspects of the Performance Solution proposed or that are affected by the application of the Performance Solution. (4) Where a Performance Requirement is proposed to be satisfied by a Performance Solution, the following steps must be undertaken: Prepare a performance-based design brief in consultation with relevant stakeholders. Carry out analysis, as proposed by the performance-based design brief. Evaluate results from (4)(b) against the acceptance criteria in the performance-based design brief. Prepare a final report that includes — all Performance Requirements and/or Deemed-to-Satisfy Provisions identified through A2G2(3) or A2G4(3) as applicable; and identification of all Assessment Methods used; and details of steps (4)(a) to (4)(c); and confirmation that the Performance Requirement has been met; and details of conditions or limitations, if any exist, regarding the Performance Solution. (5) A Performance Solution cannot be used to satisfy a … building with a rise in storeys of 3 or more. Limitations Where compliance with B1P1(2) or H1P1(2) is proposed to be satisfied by a Performance Solution for materials included in B1D4(a) to (f) or clauses 2.2.4(d) and 2.2.4(g) to (k) of the ABCB Housing Provisions, the Performance Solution must be — achieved by demonstrating the solution is at least equivalent to the Deemed-to-Satisfy Provisions in accordance with A2G2(1)(b); and shown to comply with the Performance Requirements through A2G2(2)(d). Notes The limitation above does not take effect until 1 year after the adoption date for NCC 2025.

Removed words are struck through; added words are highlighted. Comparison of the text only.

The national clause