Performance Requirement · NCC 2022 Volume Three

C2P7 Damage

Part C2 Sanitary drainage systems · NCC 2019: CP2.1

Open C2P7 on NCC Online ↗

(1) A sanitary drainage system must avoid damage from root penetration, superimposed loads or ground movement.

(2) A sanitary drainage system must avoid damage to existing buildings or siteworks.

(3) A sanitary drainage system must avoid damage to the Network Utility Operator's sewerage system or other approved disposal system.

Notes

There are no Deemed-to-Satisfy Provisions for sanitary drainage systems to address ground movement.

Changed in NCC 2025. See NCC 2025 Volume Three C2P7, or show what changed.

(1) A Damage to sanitary drainage system systems from superimposed loads must avoid damage be avoided. (2) Damage to sanitary drainage systems from ground movement must be avoided. (3) Damage to sanitary drainage systems from root penetration, superimposed loads or ground movement. (2) A sanitary drainage system penetration must avoid damage to existing buildings or siteworks. (3) A sanitary drainage system must avoid damage be avoided. (4) Damage to the Network Utility Operator's sewerage system or other any approved disposal system. Notes There are no Deemed-to-Satisfy Provisions for system must be avoided. (5) Damage to siteworks or existing buildings from a sanitary drainage systems to address ground movement. must be avoided.

Removed words are struck through; added words are highlighted. Comparison of the text only.

Defined terms used