Victoria variation · NCC 2022 Volume Three
VIC B2P3 Velocity
Part B2 Heated water services · varies B2P3 Velocity
Delete subclause B2P3(1) and insert VIC B2P3(1) as follows:
The water velocity in heated water service pipework up to 65 °C must not exceed—
3 m/s for more than 1% of the time that water is required during the peak hour in non-circulatory heated water systems; and
1.2 m/s for the flow and 1.0 m/s for the return of a copper circulatory heated water service for more than 1% of the time that water is required during the peak hour; and
1.0 m/s for the flow and return of a circulatory heated water service using other materials for more than 1% of the time that the water is required during the peak hour.
Not in NCC 2025. No VIC B2P3 in NCC 2025 Volume Three.