8.2.2 Installation of windows
Part 8.2 Windows and external glazed doors
Varied in WA. Check the variation for your state.
Windows must be installed in accordance with the following:
Structural building loads must not be transferred to the window assembly.
A minimum 10 mm gap must be provided between the top of the window assembly and any load bearing framing or masonry wall element.
The requirements of (b) may be increased where necessary to allow for frame settlement over wide openings.
Packing, if provided between each window assembly and the frame, must be—
located along each side and bottom; and
fixed to ensure the sides and bottom of the window assembly remain straight; and
clear of any flashing material.