NT 13.7.3 Central heating water piping

NT Part 13.7 Services · varies 13.7.3 Central heating water piping

Open on NCC Online ↗

Insert NT clause 13.7.3 in clause 13.7.3 as follows:

(1) Central heating water piping that is not within a conditioned space must be thermally insulated to achieve the minimum Total R-Value of 0.6.

(2) Internal piping including—

flow and return piping that is—

within an unventilated wall space; or

within an internal floor between storeys; or

between ceiling insulation and a ceiling; and

heated water piping encased in a concrete floor slab (except that which is part of a floor heating system), must in all climate zones, have a minimum material R-Value of 0.4.

(3) All piping located outside a building, or within a ventilated wall space, subfloor or roof space must have a minimum material R-Value of 0.6.

Changed since NCC 2022. See ABCB Housing Provisions 2022 NT 13.7.3, or show what changed.

Insert NT clause 13.7.3 in clause 13.7.3 as follows: (1) Central heating water piping that is not within a … roof space must have a minimum material R-Value of 0.6.

Removed words are struck through; added words are highlighted. Comparison of the text only.

The national clause