Table 5.6.5c Placement of wall ties

Part 5.6 Masonry components and accessories

Open Table 5.6.5c on NCC Online ↗
LocationPlacement of wall ties
Unsupported panel sides and edges of openingsWithin 300 mm of panel side or edge
Top of veneer panels and top of panels under openingsWithin 300 mm or two courses (whichever is the lesser) of the top of veneer
Bottom of veneer panel in masonry rebate sealed with liquid applied damp-proof courseWithin 300 mm or two courses (whichever is the lesser) from the bottom of the veneer
Bottom of veneer panel in masonry rebate with membrane damp-proof courseIn each of the first two courses
Intersection of internal walls and external walls350 mm vertically or 3-4 courses
Where articulation joints occurAt both sides of the articulation joint within 300 mm from the joint
Engaged piersWithin 200 mm of the top of the pier

Bottom of veneer panel supported on steel lintel

Table Notes

Ties to be embedded a minimum of 50 mm into each masonry leaf.

Masonry wall ties must be installed in such a manner as to prevent moisture travelling along the tie to the inner leaf of masonry or the frame.

Table for 5.6.5 Wall ties

Same wording in ABCB Housing Provisions 2022. See ABCB Housing Provisions 2022 Table 5.6.5c.