Performance Requirement · NCC 2025 Volume Three

B1P2 Velocity

Part B1 Cold water services · NCC 2019: BP1.2

Open B1P2 on NCC Online ↗

(1) Water velocity within cold water service pipework must not exceed 3 metres per second for no less than 99% of the time that water is required during the peak hour.

(2) Water velocity within cold water valves and devices must ensure the correct functioning of fixtures and appliances.

Changed since NCC 2022. See NCC 2022 Volume Three B1P2, or show what changed.

Cold (1) Water velocity within cold water service pipework must ensure that the pipework water velocity does not exceed 3 metres per second for more no less than 1% 99% of the time that water is required during the annual peak hour. (2) Water velocity within cold water valves and devices must ensure the correct functioning of fixtures and appliances.

Removed words are struck through; added words are highlighted. Comparison of the text only.

Defined terms used