B7D1 Deemed-to-Satisfy Provisions

Part B7 Rainwater storage · NCC 2019: B6.1

Open B7D1 on NCC Online ↗

(1) Where a Deemed-to-Satisfy Solution is proposed, Performance Requirements B7P1 and B7P5 are satisfied by complying with B7D3 and B7D4.

(2) Where a Performance Solution is proposed, the relevant Performance Requirements must be determined in accordance with A2G2 (3) and A2G4 (3) as applicable.

Changed since NCC 2022. See NCC 2022 Volume Three B7D1, or show what changed.

(1) Where a Deemed-to-Satisfy Solution is proposed, Performance Requirements B7P1 and B7P4 B7P5 are satisfied by complying with B7D2 B7D3 and B7D3. B7D4. (2) Where a Performance Solution is proposed, the relevant Performance Requirements must be determined in accordance with A2G2(3) A2G2 (3) and A2G4(3) A2G4 (3) as applicable. Notes There are no Deemed-to-Satisfy Solutions for B7P2 and B7P3.

Removed words are struck through; added words are highlighted. Comparison of the text only.

Clauses referred to

Defined terms used