A2G2 Performance Solution
Part A2 Compliance with the NCC · NCC 2019: A2.2
(1) Subject to (5), a Performance Solution is achieved by demonstrating—
compliance with all relevant Performance Requirements; or
the solution is at least equivalent to the Deemed-to-Satisfy Provisions.
(2) Subject to (5), a Performance Solution must be shown to comply with the relevant Performance Requirements through one or a combination of the following Assessment Methods:
Evidence of suitability in accordance with Part A5 that shows the use of a material, product, plumbing and drainage product, form of construction or design meets the relevant Performance Requirements.
A Verification Method including the following:
The Verification Methods provided in the NCC.
Other Verification Methods, accepted by the appropriate authority that show compliance with the relevant Performance Requirements.
Expert Judgement.
Comparison with the Deemed-to-Satisfy Provisions.
(3) Where a Performance Requirement is satisfied entirely by a Performance Solution, in order to comply with (1) the following method must be used to determine the Performance Requirement or Performance Requirements relevant to the Performance Solution:
Identify the relevant Performance Requirements from the Section or Part to which the Performance Solution applies.
Identify Performance Requirements from other Sections or Parts that are relevant to any aspects of the Performance Solution proposed or that are affected by the application of the Performance Solution.
(4) Where a Performance Requirement is proposed to be satisfied by a Performance Solution, the following steps must be undertaken:
Prepare a performance-based design brief in consultation with relevant stakeholders.
Carry out analysis, as proposed by the performance-based design brief.
Evaluate results from (4)(b) against the acceptance criteria in the performance-based design brief.
Prepare a final report that includes—
all Performance Requirements and/or Deemed-to-Satisfy Provisions identified through A2G2(3) or A2G4(3) as applicable; and
identification of all Assessment Methods used; and
details of steps (4)(a) to (4)(c); and
confirmation that the Performance Requirement has been met; and
details of conditions or limitations, if any exist, regarding the Performance Solution.
(5) Where compliance with B1P1(2) or H1P1(2) is proposed to be satisfied by a Performance Solution for materials included in B1D4(a) to (f) or clauses 2.2.4(d) and 2.2.4(g) to (k) of the ABCB Housing Provisions, the Performance Solution must be achieved by demonstrating the solution is at least equivalent to the Deemed-to-Satisfy Provisions.
Limitations
A2G2(2)(c) does not apply to demonstrating compliance with Volume One Performance Requirements B1P1(2), C1P1, C1P2, C1P3, C1P4, C1P5, C1P6, C1P7, C1P8, C1P9, D1P1, D1P2, D1P3, D1P4, D1P5, D1P6, D1P7, D1P8, D1P9, D1P10, E1P1, E1P2, E1P3, E1P4, E1P5, E1P6, E2P1, E2P2, E3P1, E3P2, E3P3, E3P4, E4P1, E4P2, E4P3 and Volume Two Performance Requirement H1P1(2), to the extent they relate to structural or fire safety.
Notes
A2G2(5) does not take effect until 1 year after the adoption date for NCC 2025.
Changed since NCC 2022. See NCC 2022 Volume Three A2G2, or show what changed.
(1) A Subject to (5), a Performance Solution is achieved by demonstrating — compliance with all … solution is at least equivalent to the Deemed-to-Satisfy Provisions. (2) A Subject to (5), a Performance Solution must be shown to comply with the relevant … conditions or limitations, if any exist, regarding the Performance Solution. (5) Where compliance with B1P1(2) or H1P1(2) is proposed to be satisfied by a Performance Solution for materials included in B1D4(a) to (f) or clauses 2.2.4(d) and 2.2.4(g) to (k) of the ABCB Housing Provisions, the Performance Solution must be achieved by demonstrating the solution is at least equivalent to the Deemed-to-Satisfy Provisions. Limitations A2G2(2)(c) does not apply to demonstrating compliance with Volume One Performance Requirements B1P1(2), C1P1, C1P2, C1P3, C1P4, C1P5, C1P6, C1P7, C1P8, C1P9, D1P1, D1P2, D1P3, D1P4, D1P5, D1P6, D1P7, D1P8, D1P9, D1P10, E1P1, E1P2, E1P3, E1P4, E1P5, E1P6, E2P1, E2P2, E3P1, E3P2, E3P3, E3P4, E4P1, E4P2, E4P3 and Volume Two Performance Requirement H1P1(2), to the extent they relate to structural or fire safety. Notes A2G2(5) does not take effect until 1 year after the adoption date for NCC 2025.
Removed words are struck through; added words are highlighted. Comparison of the text only.
State and territory variations all clauses side by side →
- NSW Replaced Delete clause A2G2 and insert NSW A2G2 as follows: (1) A Performance Solution is achieved by demonstrating— compliance with all…
- VIC Replaced Delete clause A2G2 and insert VIC A2G2 as follows: (1) A Performance Solution is achieved by demonstrating— compliance with all…
Clauses referred to
- A2G4 A combination of solutions
- B1P1 Cold water supply
- B1D4 Bushfire prone areas
- C1P1 Disposal
- C1P2 Access
- C1P3 Water efficiency
- C1P4 Uncontrolled discharge
- C1P5 Ventilation
- C1P6 Contamination
- C1P7 Damage
- D1P1 Undue noise
- D1P2 Excessive noise
- E1P1 Facilities for people with disability