Deemed-to-Satisfy Provision · NCC 2025 Volume Two

H1D3 Site preparation

Part H1 Structure · NCC 2019: 3.1.1, 3.1.2, 3.1.4

Open H1D3 on NCC Online ↗
Varied in QLD. Check the variation for your state.

(1) Performance Requirement H1P1 is satisfied for earthworks associated with the construction of a building or structure if they are in accordance with Part 3.2 of the ABCB Housing Provisions, provided that the site is classified as A, S, M, H or E in accordance with 4.2.2 of the ABCB Housing Provisions and the work is undertaken in normal site conditions.

(2) Performance Requirement H1P1 is satisfied for an earth retaining structure associated with the construction of a building or structure if it is designed and constructed in accordance with AS 4678.

(3) Compliance with Part 3.4 of the ABCB Housing Provisions satisfies Performance Requirement H1P1 for termite risk management.

Same wording in NCC 2022 Volume Two. See NCC 2022 Volume Two H1D3.

State and territory variations all clauses side by side →