Deemed-to-Satisfy Provision · NCC 2022 Volume Two
H1D3 Site preparation
Part H1 Structure · NCC 2019: 3.1.1, 3.1.2, 3.1.4
Varied in QLD. Check the variation for your state.
(1) Performance RequirementH1P1 is satisfied for earthworks associated with the construction of a building or structure if they are in accordance with Part 3.2 of the ABCB Housing Provisions, provided that the site is classified as A, S, M, H or E in accordance with 4.2.2 of the ABCB Housing Provisions and the work is undertaken in normal site conditions.
(2) Performance RequirementH1P1 is satisfied for an earth retaining structure associated with the construction of a building or structure if it is designed and constructed in accordance with AS 4678.
(3) Compliance with Part 3.4 of the ABCB Housing Provisions satisfies Performance Requirement H1P1 for termite risk management.
Same wording in NCC 2025 Volume Two. See NCC 2025 Volume Two H1D3.