Deemed-to-Satisfy Provision · NCC 2025 Volume One

C2D13 Fire-protected timber: Concession

Part C2 Fire resistance and stability · NCC 2019: C1.13

Open C2D13 on NCC Online ↗

Fire-protected timber may be used wherever an element is required to be non-combustible, provided—

the building is—

a separate building; or

a part of a building—

which only occupies part of a storey, and is separated from the remaining part by a fire wall; or

which is located above or below a part not containing fire-protected timber and the floor between the adjoining parts is provided with an FRL not less than that prescribed for a fire wall for the lower storey; and

the building has an effective height of not more than 25 m; and

the building has a sprinkler system (other than a FPAA101D or FPAA101H system) throughout complying with Specification 17; and

any insulation installed in the cavity of the timber building element to have an FRL is non-combustible; and

cavity barriers are provided in accordance with Specification 9.

Same wording in NCC 2022 Volume One. See NCC 2022 Volume One C2D13.
Can't meet C2D13? A Performance Solution must meet the Performance Requirements it satisfies: C1P1, C1P2, C1P3, C1P4, C1P5, C1P6, C1P7, C1P8, C1P9. Start a Performance Solution →

Defined terms used