E2D19 Class 9b – assembly buildings: theatres and public halls (not listed in E2D18) including lecture theatres and cinema/auditorium complexes

Part E2 Smoke hazard management · NCC 2019: NSW Table E2.2b, Table E2.2b

Open E2D19 on NCC Online ↗
Varied in NSW. Check the variation for your state.

(1) This clause applies to a Class 9b assembly building where the building or part of the building is used as a theatre or public hall not listed in E2D18 and includes lecture theatres and cinema/auditorium complexes.

(2) A building or part of a building referred to in (1)—

must be provided with automatic shutdown of any air-handling system (other than ventilation systems installed in accordance with Sections 5 and 6 of AS 1668.1) which does not form part of the smoke hazard management system, on the activation of—

smoke detectors installed complying with Specification 20; and

any other installed fire detection and alarm system, including a sprinkler system complying with Specification 17; and

other than in the case of a school lecture theatre, where the floor area of the Class 9b part of a fire compartment is more than 2000 m2, the Class 9b building or part must be provided with—

an automatic smoke exhaust system complying with Specification 21; or

if the building is single storey, automatic smoke-and-heat vents complying with Specification 22; or

if the floor area of the fire compartment is not more than 5000 m2 and the building has a rise in storeys of not more than 2—

an automatic smoke detection and alarm system complying with Specification 20; or

a sprinkler system (other than a FPAA101D or FPAA101H system) complying with Specification 17.

Changed since NCC 2022. See NCC 2022 Volume One E2D19, or show what changed.

(1) This clause applies to a Class 9b assembly building … provided with automatic shutdown of any air-handling system (other than miscellaneous exhaust air ventilation systems installed in accordance with Sections 5 and 6 of … a school lecture theatre, where the floor area of the Class 9b part of a fire compartment is more than 2000 m2 m2, the Class 9b building or part must be provided with — an automatic smoke exhaust system complying with Specification 21; … than a FPAA101D or FPAA101H system) complying with Specification 17.

Removed words are struck through; added words are highlighted. Comparison of the text only.

Can't meet E2D19? A Performance Solution must meet the Performance Requirements it satisfies: E2P1, E2P2. Start a Performance Solution →

State and territory variations all clauses side by side →

Clauses referred to

Defined terms used